Local traffic restrictions and roadworks from 30 July

Traffic restrictions and roadworks starting within the next week for the Reepham district have been issued by roadworks.org on 30 July 2019
 
A1067 Fakenham Road, Bawdeswell
31 July – 2 August
Delays likely Traffic control (Stop/Go boards)
Works location: Along entire stretch
Works description: Gully cleaning
Responsibility for works: Norfolk
Works reference: HU607A1067/1250LTGU
 
A1067 Fakenham Road, Great Witchingham
31 July – 2 August
Delays likely Traffic control (Stop/Go boards)
Works location: Along entire length
Works description: Gully cleaning
Responsibility for works: Norfolk
Works reference: HU607A1067/1232LTGU5
 
A1067 Fakenham Road, Great Witchingham
1–5 August
Delays likely Traffic control (Stop/Go boards)
Works location: Near Morse Close junc
Works description: Footway patching.
Responsibility for works: Norfolk
Works reference: HU608125340LTPA
 
A1067 Main Road, Sparham
31 July – 2 August
Delays likely Traffic control (Stop/Go boards)
Works location: Along entire length
Works description: Gully Cleaning
Responsibility for works: Norfolk
Works reference: HU607A1067/1238LTGU1
 
A1067 Norwich Road, Foxley
31 July – 2 August
Delays likely Traffic control (Stop/Go boards)
Works location: Along entire length
Works description: Gully cleaning
Responsibility for works: Norfolk
Works reference: HU607A1067/1260LTGU2
 
A1067 Sparham Hill, Sparham
31 July – 2 August
Delays likely Traffic control (Stop/Go boards)
Works location: entire length
Works description: Gully cleaning
Responsibility for works: Norfolk
Works reference: HU607A1067/1232LTGU3
 
B1145 Dereham Road, Reepham
30 July – 1 August
Delays likely Traffic control (multi-way signals)
Works location: From junction of School Road to junc of Broomhill Lane on Dereham Road
Works description: REEPHAM R13 - DSLAM 584147 - desiliting – required on sections of duct in order to complete spine route to exchange area
Responsibility for works: Openreach
Works reference: BC005MU1WSEP00IBWCNKMH16
 
B1145 Reepham Road, Bawdeswell
1 August
Delays likely Traffic control (two-way signals)
Works location: Opposite Pigmans House
Works description: Two-way lights required for one day 0930-1530hrs to enable new aerial cable to be erected
Responsibility for works: Openreach
Works reference: BC005CR4W0000LUXCV557737
 
B1145 Station Road, Reepham
30 July – 1 August
Delays likely Traffic control (multi-way signals)
Works location: At the junction with Dereham Road on station road
Works description: REEPHAM R13 - DSLAM 584147 - traffic management to facilitate BT Openreach fibre cabling works – with no excavation. Portable traffic signal head only, linked to notice/permit number BC005MU1WSEP00IBWCNKMH13, BC005MU1WSEP00IBWCNKMH16
Responsibility for works: Openreach
Works reference: BC005MU1WSEP00IBWCNKMH14
 
B1354/B1149 Briston Road, Saxthorpe
30 July – 1 August
Delays likely Traffic control (Stop/Go boards)
Works location: 88m west of 14361 Edgefield Road Jt 134m NW of entrance to Bungalows Prospect Point
Works description: Lining and stud installation
Responsibility for works: Norfolk
Works reference: HU607N313BALTRM
 
Billingford Road, Bintree
1–3 August
Delays likely Road closure
Works location: Billingford Road 100m from jnc of Fakenham Road A1067
Works description: Carriageway resurfacing
Responsibility for works: Norfolk
Works reference: HU606PM4126LTSC18
 
Heydon Road, Cawston
30 July – 5 August
Delays likely Road closure
Works location: Junction of Southgate Lane to the northern boundary of Hill House
Works description: Road closure required to enable a temporary access to the farmer’s field and our site through existing hedgerow
Responsibility for works: Anglian Water
Works reference: AD044WAT-06966-04-06
 
Heydon Road, Salle
5–9 August
Delays likely Road closure
Works location: From outside Salle Lodge Heydon Road to approx 64m SE on Heydon Road
Works description: REEPHAM 15 - DSLAM 607522, 607524 - street cabinet and power installation. Excavate to lay approx 38m BT ducts, lay concrete plinth, stand cab, excavate and lay 26m of duct to power pole for overhead connection, reinstate, check and clear site
Responsibility for works: Openreach
Works reference: BC006MU1WSEP00IBY1VFVX01
 
Market Place, Reepham
30 July – 1 August
Delays likely Traffic control (multi-way signals)
Works location: At the junction of School Road on Market Place
Works description: REEPHAM R13 - DSLAM 584147 - traffic management to facilitate BT Openreach fibre cabling works – with no excavation. Portable traffic signal head only, linked to notice/permit number BC005MU1WSEP00IBWCNKMH13, BC005MU1WSEP00IBWCNKMH16
Responsibility for works: Openreach
Works reference: BC005MU1WSEP00IBWCNKMH15
 
Old School Road, Guestwick
5–7 August
Delays likely Road closure
Works location: approx 90m west of Old School House
Works description: New water connection for The White House
Responsibility for works: Anglian Water
Works reference: AD03010533446
 
Peddlars Turnpike, Foulsham
5–9 August
Delays likely Road closure
Works location: junction with Reepham Road on Peddlars Turnpike
Works description: FOULSHAM 646094 - Planned maintenace – Lay approx 6m of duct 54/56 in verge/cw to link existing BT boxes to facilitate spine cabling works
Responsibility for works: Openreach
Works reference: BC006MU1WBAUSEIBYN4KLS02
 
Reepham Road, Foulsham
5–9 August
Delays likely Road closure
Works location: junction with Peddlars Turnpike on Reepham Road
Works description: FOULSHAM 646094 - planned maintenace – lay approx 15m of duct 54/56 in verge/cw to link existing BT boxes to facilitate spine cabling works
Responsibility for works: Openreach
Works reference: BC006MU1WBAUSEIBYN4KLS01
 
School Road, Reepham
30 July – 1 August
Delays likely Traffic control (multi-way signals)
Works location: From junction with Dereham Road to junc with Robins Lane on School Road
Works description: REEPHAM R13 - DSLAM 584147 - desiliting – eequired on sections of duct in order to complete spine route to exchange area
Responsibility for works: Openreach
Works reference: BC005MU1WSEP00IBWCNKMH13
 
Wood Dalling Road, Thurning
1–2 August
Delays likely Road closure
Works location: From opposite track leading to Thurning Hall to junction of Hindolveston Road on Wood Dalling Road
Works description: Access required to overhead BT structure to repair service - no structural changes. Work being carried out on existing BT plant
Responsibility for works: Openreach
Works reference: BC005CC1W0002AUGEA4CYU30
 
Guestwick Road, Foulsham
30 July – 1 August
Delays possible Traffic control (Stop/Go boards)
Works location: At the junction with Reepham Road on Guestwick Road
Works description: FOULSHAM 532866 - traffic management to facilitate BT Openreach fibre cabling works
Responsibility for works: Openreach
Works reference: BC005MU1WSEP00WAJW0P1T13
 
Reepham Road, Foulsham
30 July – 1 August
Delays possible Traffic control (Stop/Go boards)
Works location: From the junction of Guestwick Road to the opposite of 12 on Reepham Road
Works description: FOULSHAM 532866 - Overlay – Lay approx 92m of duct 54/56 in verge, carriageway to link existing BT Boxes to facilitate spine cabling works
Responsibility for works: Openreach
Works reference: BC005MU1WSEP00WAJW0P1T12
 
Well Lane, Sparham
31 July – 1 August
Delays possible Some carriageway incursion
Works location: Opposite 2 Well Lane
Works description: BAWDESWELL 4 - DSLAM 656359, 656362 - remedial works - to clear internal defect verge, carriageway
Responsibility for works: Openreach
Works reference: BC005MU1WSEP00IBYU2AMH02
 
Heydon Road, Corpusty
31 July – 2 August
Delays unlikely Some carriageway incursion
Works location: opposite 4, in verge
Works description: Enhanced metering
Responsibility for works: Anglian Water
Works reference: AD04253326798
 
Ketts Lane, Little Witchingham
31 July – 2 August
Delays unlikely No carriageway incursion
Works location: On grass verge
Works description: Engineer to carry out a hand dig in grass verge to expose a buried cable in order to repair service and then to provide a footway box on backfill. Should a footway box not be possible then surface will be reinstated. *****Fault Report EA4LYA38 ****
Responsibility for works: Openreach
Works reference: BC005CC1W00EA4LYA38JUL31
 
Old Hall Lane, Foulsham
2–5 August
Delays unlikely Some carriageway incursion
Works location: from the junction of Reepham Road to side of Macallens Farm
Works description: FOULSHAM 9 - DSLAM 548637, 548648 - remedial works - to clear internal defect in verge/carriageway
Responsibility for works: Openreach
Works reference: BC006MU1WSEP00IBUR6RAK03