Concerns about the proposed cable route linking the Pettywell Solar Farm to the Salle substation near Cawston were raised at November’s meeting of Reepham Town Council.
Several residents questioned the scale of the planned works and potential disruption to Marriott’s Way and Kerdiston Road (pictured), noting that the working area for the trench could be from eight to 15 metres wide, and expressing doubts about the long-term benefits of the scheme for Reepham.
Cllr David Jackson reported that the developer, Albanwise Synergy, had clarified that the quoted widths were indicative rather than fixed. The actual working area would vary according to local conditions, with wider sections allowing construction materials and machinery to be positioned close to the excavation to improve efficiency. In more constrained locations, narrower working arrangements could be used.
Residents also voiced concerns that significant gaps could be created where the route crosses existing hedgerows. Albanwise said only narrow sections of hedgerow would need to be temporarily removed to allow the trench to pass through and that affected areas would be replanted after the work is completed.
The proposed 6.4 km cable route runs mainly to the north of Reepham and has been designed to avoid the town centre and other sensitive locations. Around 77% of the route will be installed across fields and privately or council-owned land, reducing the need for works on public roads and helping to limit disruption. Sections that follow roads will remain within the existing highway corridor.
The town council has agreed to the laying of cables across the northern end of the Stimpson’s Piece recreation ground, along the treeline, to reduce the impact on the local highway network.
Construction is expected to take between six and nine months, with work currently anticipated to begin in early or mid-2027 and continue into early 2028. The project will involve digging trenches for underground ducts, installing the cables and carrying out jointing works at various points along the route.
Council chair Hetty Selwyn noted that the town council had opposed the original solar farm planning application. However, following its approval, the council had worked with Albanwise to secure a cable route that would minimise disruption to traffic and residents.
She also highlighted that the developer has agreed to contribute £25,000 towards the town’s proposed new skatepark.
Albanwise has since added that a community benefit fund will also be available to support local projects and initiatives.
The 40 MW Pettywell solar project, which is planned to operate for 40 years, will generate clean energy for around 14,000 homes.
See our earlier story:
Solar farm cable route plans published
Photo: Reepham Life/Reepham Community Press